Estimation, Costing & Valuation Notes for UPSSSC JE | Methods, Rate Analysis, Valuation | Hindi

2.8 рдиिрд░्рдоाрдг рдЕрдиुрдоाрди рдПрд╡ं рдоूрд▓्рдпांрдХрди
(Estimation, Costing & Valuation)
UPSSSC JE – Complete Notes

Exam Focus: рдпрд╣ topic UPSSSC JE / SSC JE рдоें Direct + Conceptual + Numerical рддीрдиों рдк्рд░рдХाрд░ рд╕े рдкूрдЫा рдЬाрддा рд╣ै।

ЁЯФ╣ 1. Estimation (рдЕрдиुрдоाрди) – Introduction

Estimation рд╡рд╣ рдк्рд░рдХ्рд░िрдпा рд╣ै рдЬिрд╕рдоें рдХिрд╕ी рднी civil engineering project рдХे рд▓िрдП required quantities рдФрд░ approximate cost рдкрд╣рд▓े рд╕े calculate рдХी рдЬाрддी рд╣ै।


рд╕рд░рд▓ рд╢рдм्рджों рдоें – “рдХाрдо рд╢ुрд░ू рд╣ोрдиे рд╕े рдкрд╣рд▓े рдпрд╣ рдкрддा рд▓рдЧाрдиा рдХि рдХिрддрдиा material рд▓рдЧेрдЧा рдФрд░ рдХिрддрдиा рдкैрд╕ा рдЦрд░्рдЪ рд╣ोрдЧा” рдЗрд╕े estimation рдХрд╣рддे рд╣ैं।

ЁЯУМ UPSSSC JE Point: Estimation is the backbone of planning, tendering and execution.

ЁЯФ╣ 2. Importance of Estimation (рдорд╣рдд्рд╡)

  • Project рдХी total cost рдЬाрдирдиे рдХे рд▓िрдП
  • Government approval рдк्рд░ाрдк्рдд рдХрд░рдиे рдХे рд▓िрдП
  • Tender prepare рдХрд░рдиे рдХे рд▓िрдП
  • Material requirement рдЬाрдирдиे рдХे рд▓िрдП
  • Labour & machinery planning рдХे рд▓िрдП
  • Time management рдПрд╡ं budget control рдХे рд▓िрдП

ЁЯУМ Exam Trick: рдЕрдЧрд░ question рдЖрдП – “Why estimation is required?” рддो answer рдоें Cost, Tender, Approval, Planning рдЬрд░ूрд░ рд▓िрдЦें।

ЁЯФ╣ 3. Types of Estimates (рдЕрдиुрдоाрдиों рдХे рдк्рд░рдХाрд░)

3.1 Preliminary / Rough Estimate

рдпрд╣ estimate project рдХे initial stage рдоें рдмрдиाрдпा рдЬाрддा рд╣ै।

  • Approximate cost
  • Based on plinth area / cubic rate
  • Administrative approval рдХे рд▓िрдП

Example: Rough cost of school building = Area × Plinth area rate

3.2 Detailed Estimate

рдпрд╣ рд╕рдмрд╕े important estimate рд╣ोрддा рд╣ै।

  • Item-wise quantities
  • Detailed drawings рдХे рдЖрдзाрд░ рдкрд░
  • Technical sanction рдХे рд▓िрдП

ЁЯУМ UPSSSC JE Favourite Line: Detailed estimate is prepared after complete drawings and specifications.

3.3 Revised Estimate

рдЬрдм original estimate рд╕े cost 5–10% рд╕े рдЬ्рдпाрджा рдмрдв़ рдЬाрдП, рддрдм revised estimate рдмрдирддा рд╣ै।

3.4 Supplementary Estimate

рдЬрдм original work рдХे рд╕ाрде additional work рд╢ाрдоिрд▓ рдХрд░рдиा рд╣ो।

3.5 Annual Repair & Maintenance Estimate

  • White washing
  • Painting
  • Minor repairs

ЁЯФ╣ 4. Methods of Estimation (рдЕрдиुрдоाрди рдХी рд╡िрдзिрдпाँ)

Estimation methods рдХा рдЙрдкрдпोрдЧ quantities рдиिрдХाрд▓рдиे рдХे рд▓िрдП рдХिрдпा рдЬाрддा рд╣ै।

4.1 Long Wall – Short Wall Method

  • Most commonly used method
  • Walls classified as Long and Short
  • Length varies at each layer

Formula:
Long wall length = Centre to centre length + half breadth
Short wall length = Centre to centre length – half breadth

ЁЯУМ Exam Note: UPSSSC JE рдоें рдЕрдХ्рд╕рд░ рдкूрдЫा рдЬाрддा рд╣ै – “Which method is most accurate?” ЁЯСЙ Answer: Long wall – Short wall method

4.2 Centre Line Method

рдЗрд╕ method рдоें рд╕рднी walls рдХी centre line length рд▓ी рдЬाрддी рд╣ै।

  • Fast method
  • Symmetrical buildings рдХे рд▓िрдП suitable
  • Calculation easy

ЁЯУМ Difference рдкूрдЫे рдЬाрдиे рдкрд░: Centre line method – Fast Long wall method – More accurate

✅ PART–1 Complete
✔ Estimation Introduction ✔ Importance ✔ Types of Estimates ✔ Methods of Estimation (Start) ЁЯСЙ Next: PART–2 • Detailed Long wall vs Centre line (Numerical) • Plinth area method • Cubical content method

2.8 Construction Estimation, Costing & Valuation
PART–2 : Methods of Estimation (Detailed)

Exam Focus: PART–2 рд╕े UPSSSC JE рдоें Direct MCQ + Numerical рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Long Wall – Short Wall Method

рдпрд╣ method рд╕рдмрд╕े accurate рдоाрдиा рдЬाрддा рд╣ै рдФрд░ government works рдоें widely used рд╣ै।

ЁЯФ╕ Principle

  • Walls рдХो Long wall рдФрд░ Short wall рдоें divide рдХिрдпा рдЬाрддा рд╣ै
  • рд╣рд░ layer (foundation, plinth, superstructure) рдоें length рдмрджрд▓рддी рд╣ै

ЁЯФ╕ Formula

Long Wall Length = C/C length + ½ breadth
Short Wall Length = C/C length – ½ breadth

ЁЯФ╕ Steps

  1. Centre to centre length find рдХрд░ें
  2. Foundation breadth determine рдХрд░ें
  3. Each layer рдХे рд▓िрдП length calculate рдХрд░ें
  4. Quantity = Length × Breadth × Depth

ЁЯУМ UPSSSC JE Note: Most accurate method = Long wall – Short wall

ЁЯФ╣ 2. Centre Line Method

рдЗрд╕ method рдоें рд╕рднी walls рдХी centre line length рд▓ी рдЬाрддी рд╣ै।

ЁЯФ╕ Principle

  • Centre line length constant рд░рд╣рддी рд╣ै
  • Quantity = Total C/L × Breadth × Depth

ЁЯФ╕ Suitability

  • Symmetrical buildings
  • Same wall thickness

ЁЯУМ Exam Point: Centre line method is fast but less accurate

ЁЯФ╣ 3. Comparison (Very Important for MCQ)

Point Long Wall Method Centre Line Method
Accuracy High Moderate
Speed Slow Fast
Complex Buildings Suitable Not suitable
Exam Preference Very High High

ЁЯФ╣ 4. Plinth Area Method

рдпрд╣ method Preliminary / Rough Estimate рдХे рд▓िрдП use рд╣ोрддी рд╣ै।

ЁЯФ╕ Formula

Cost = Plinth Area × Plinth Area Rate

ЁЯФ╕ Plinth Area includes

  • Wall thickness
  • Rooms, verandah
  • Staircase

ЁЯФ╕ Excludes

  • Courtyard
  • Open terrace

ЁЯУМ MCQ: Plinth area method is used for Administrative approval

ЁЯФ╣ 5. Cubical Content Method

рдпрд╣ method plinth area method рд╕े рдЬ्рдпाрджा accurate рд╣ोрддी рд╣ै।

ЁЯФ╕ Formula

Cubic Content = Plinth Area × Height

ЁЯФ╕ Uses

  • Multi-storey buildings
  • Height variation projects

ЁЯУМ Exam Trick: Cubical content method > Plinth area method (accuracy wise)

✅ PART–2 Complete
✔ Long wall – Short wall (Detail) ✔ Centre line method ✔ Comparison table ✔ Plinth area method ✔ Cubical content method ЁЯСЙ Next: PART–3 • Detailed Estimate preparation • BOQ (Bill of Quantities) • Measurement rules (IS 1200)

2.8 Construction Estimation, Costing & Valuation
PART–3 : Detailed Estimate, BOQ & IS 1200

Exam Focus: PART–3 рд╕े Direct Theory + MCQ + Conceptual Questions рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Detailed Estimate (рд╡िрд╕्рддृрдд рдЕрдиुрдоाрди)

Detailed Estimate рд╡рд╣ рдЕрдиुрдоाрди рд╣ै рдЬिрд╕рдоें project рдХे рд╕рднी items рдХी quantity, rate рдФрд░ total cost item-wise calculate рдХी рдЬाрддी рд╣ै।

ЁЯФ╕ Purpose

  • Technical sanction рдк्рд░ाрдк्рдд рдХрд░рдиे рдХे рд▓िрдП
  • Exact project cost рдЬाрдирдиे рдХे рд▓िрдП
  • Tendering process рдХे рд▓िрдП

ЁЯФ╕ Requirements

  • Complete drawings (Plan, Elevation, Section)
  • Specifications
  • Current Schedule of Rates (SOR)

ЁЯФ╕ Steps to Prepare Detailed Estimate

  1. Study drawings carefully
  2. Calculate quantities item-wise
  3. Apply correct unit of measurement
  4. Multiply quantity with rate
  5. Add contingencies & work charged establishment

ЁЯУМ UPSSSC JE Note: Detailed estimate is prepared only after complete drawings are available.

ЁЯФ╣ 2. Bill of Quantities (BOQ)

BOQ рд╡рд╣ document рд╣ै рдЬिрд╕рдоें рд╕рднी construction items рдХी description, quantity, unit рдФрд░ rate рджी рдЬाрддी рд╣ै।

ЁЯФ╕ Purpose of BOQ

  • Tender comparison
  • Fair competition
  • Payment calculation

ЁЯФ╕ Typical BOQ Format

Item No. Description Unit Quantity Rate Amount
1 Earthwork in excavation 50 ₹200 ₹10,000
2 Brick masonry 30 ₹5,000 ₹1,50,000

ЁЯУМ Exam Point: BOQ helps in transparent tendering.

ЁЯФ╣ 3. Measurement Rules as per IS 1200

IS 1200 code рдоें civil works рдХी standard measurement rules рджिрдП рдЧрдП рд╣ैं।

ЁЯФ╕ General Rules

  • All dimensions in metre
  • Volume in cubic metre (m³)
  • Area in square metre (m²)
  • Length in running metre (m)

ЁЯФ╕ Important IS 1200 Measurement Rules (PYQ Favourite)

  • Earthwork measured in
  • Concrete measured in
  • Brickwork measured in
  • Plastering measured in
  • Painting measured in
  • Steel reinforcement measured in kg or tonne
  • Formwork measured in

ЁЯУМ MCQ Tip: “Formwork is measured in?” →

ЁЯФ╕ Deductions in Measurement

  • Openings < 0.1 m² → No deduction
  • Openings > 0.1 m² → Deduction required
✅ PART–3 Complete
✔ Detailed Estimate ✔ BOQ with format ✔ IS 1200 measurement rules ЁЯСЙ Next: PART–4 • Analysis of Rates • Labour, Material & Tools • Profit, Overheads, Lead & Lift

2.8 Construction Estimation, Costing & Valuation
PART–4 : Analysis of Rates

Exam Focus: Rate Analysis рд╕े UPSSSC JE рдоें Direct Numerical + MCQ рдЖрддे рд╣ैं।

ЁЯФ╣ 1. Rate Analysis – Introduction

Rate Analysis рд╡рд╣ рдк्рд░рдХ्рд░िрдпा рд╣ै рдЬिрд╕рдоें рдХिрд╕ी item of work рдХी unit cost calculate рдХी рдЬाрддी рд╣ै।

Rate Analysis рдмрддाрддा рд╣ै рдХि 1 unit work (рдЬैрд╕े 1 m³ concrete) рдХो рдХрд░рдиे рдоें material, labour, T&P, overheads рдФрд░ profit рдХिрддрдиा рд▓рдЧेрдЧा।

ЁЯУМ Exam Line: Rate analysis determines the fair cost of an item of work.

ЁЯФ╣ 2. Components of Rate Analysis

  • Cost of Materials
  • Cost of Labour
  • Tools & Plants (T&P)
  • Overheads
  • Contractor’s Profit

ЁЯФ╣ 3. Cost of Materials

Material cost includes:

  • Basic cost at source
  • Carriage (Lead & Lift)
  • Wastage
  • Royalties & taxes

ЁЯУМ Lead: Horizontal distance of material transport
ЁЯУМ Lift: Vertical distance of material transport

ЁЯФ╣ 4. Cost of Labour

Labour cost depends on:

  • Out-turn of labour
  • Wages per day
  • Type of work

ЁЯУМ Out-turn: Quantity of work done by a labour in one day.

ЁЯФ╣ 5. Tools & Plants (T&P)

T&P include:

  • Small tools
  • Machinery
  • Scaffolding

Usually T&P charges are taken as 1–2% of estimated cost.

ЁЯФ╣ 6. Overheads

Overheads are indirect expenses:

  • Office expenses
  • Supervision
  • Electricity & water
  • Insurance

ЁЯУМ Exam Point: Overheads are generally taken as 2–5% of total cost.

ЁЯФ╣ 7. Contractor’s Profit

Contractor profit ensures:

  • Business sustainability
  • Risk coverage

ЁЯУМ Standard Profit: 8–10% of total cost (UPSSSC JE favourite)

✅ PART–4 Complete
✔ Rate analysis basics ✔ Material, Labour, T&P ✔ Lead & Lift ✔ Overheads & Profit ЁЯСЙ Next: PART–5 • Rate Analysis Numericals • Standard Out-turn values • Cement, Concrete, Brickwork analysis

2.8 Construction Estimation, Costing & Valuation
PART–5 : Rate Analysis – Numericals & Out-turn

Exam Focus: PART–5 рд╕े Direct Numerical (10–15 marks) рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Standard Out-turn (Labour Constants)

Item of WorkOut-turn (per day)
Brickwork in CM (1:6)1.25 m³ / mason
Plain Cement Concrete (1:2:4)2.5 m³ / gang
Plastering 12 mm thick10 m² / mason
Earthwork (ordinary soil)2.8 m³ / labour
Reinforcement fixing100 kg / fitter

ЁЯУМ PYQ Tip: Out-turn values рд╕ीрдзे MCQ рдоें рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 2. Rate Analysis of Brickwork (1 m³)

ЁЯФ╕ Data (Typical)

  • No. of bricks ≈ 500 bricks/m³
  • Cement mortar = 1:6
  • Mortar quantity ≈ 0.30 m³

ЁЯФ╕ Material Calculation

  • Cement = (1/7) × 0.30 = 0.043 m³ ≈ 1.25 bags
  • Sand = (6/7) × 0.30 = 0.257 m³

ЁЯФ╕ Labour (Typical)

  • Mason = 1 No.
  • Helper = 1 No.

ЁЯУМ Exam Line: Brickwork rate = Material + Labour + T&P + Overheads + Profit

ЁЯФ╣ 3. Rate Analysis of PCC (1 m³, 1:2:4)

ЁЯФ╕ Dry Volume

Dry volume = 1 × 1.54 = 1.54 m³

ЁЯФ╕ Material Calculation

  • Cement = (1/7) × 1.54 = 0.22 m³ ≈ 6.3 bags
  • Sand = (2/7) × 1.54 = 0.44 m³
  • Aggregate = (4/7) × 1.54 = 0.88 m³

ЁЯФ╕ Labour

  • Mason = 0.5
  • Helper = 2–3

ЁЯУМ PYQ: Dry volume factor for concrete = 1.54

ЁЯФ╣ 4. Rate Analysis of Plaster (12 mm, 1:6)

ЁЯФ╕ Volume of Mortar

Volume = Area × Thickness = 10 m² × 0.012 = 0.12 m³

ЁЯФ╕ Materials

  • Cement = (1/7) × 0.12 = 0.017 m³ ≈ 0.5 bag
  • Sand = (6/7) × 0.12 = 0.103 m³

ЁЯФ╕ Labour

  • Mason = 1
  • Helper = 1

ЁЯФ╣ 5. Quick Numerical (Exam Type)

Q. Calculate cement bags required for 1 m³ PCC (1:2:4).

Ans: Cement ≈ 6.3 bags

ЁЯФ╣ 6. Common Mistakes (Avoid in Exam)

  • Dry volume factor рднूрд▓ рдЬाрдиा
  • Wastage not considered
  • Profit & overheads miss рдХрд░рдиा
  • Wrong unit (m² vs m³)
✅ PART–5 Complete
✔ Standard out-turn table ✔ Brickwork, PCC, Plaster analysis ✔ Solved numericals ✔ Exam tips ЁЯСЙ Next: PART–6 • Valuation (Market, Scrap, Salvage) • Sinking Fund & Depreciation • Capitalised Value (PYQ)

2.8 Construction Estimation, Costing & Valuation
PART–6 : Valuation, Depreciation & Sinking Fund

Exam Focus: Valuation рд╕े UPSSSC JE рдоें Direct Definition + Formula + MCQ рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Valuation (рдоूрд▓्рдпांрдХрди) – Introduction

Valuation рд╡рд╣ рдк्рд░рдХ्рд░िрдпा рд╣ै рдЬिрд╕рдХे рдж्рд╡ाрд░ा рдХिрд╕ी property рдпा structure рдХा present worth (рд╡рд░्рддрдоाрди рдоूрд▓्рдп) determine рдХिрдпा рдЬाрддा рд╣ै।

ЁЯУМ Exam Line: Valuation is the art of estimating the present value of a property.

ЁЯФ╕ Purpose of Valuation

  • Sale & purchase of property
  • Rent fixation
  • Tax assessment
  • Insurance
  • Loan & mortgage

ЁЯФ╣ 2. Types of Value (Very Important)

2.1 Market Value

Market value рд╡рд╣ price рд╣ै рдЬिрд╕ рдкрд░ property open market рдоें рдмिрдХ рд╕рдХрддी рд╣ै।

ЁЯУМ Depends on: Demand, location, utility

2.2 Book Value

Book value = Original cost – Depreciation

2.3 Capitalised Value

Capitalised value = Net annual income × Years’ Purchase

ЁЯУМ Exam Formula:
Capitalised Value = Net income / Rate of interest

2.4 Rental Value

Property рд╕े рдоिрд▓рдиे рд╡ाрд▓ा annual rent।

ЁЯФ╣ 3. Scrap Value & Salvage Value

3.1 Scrap Value

Structure рдХे demolition рдХे рдмाрдж material рдмेрдЪрдХрд░ рдоिрд▓рдиे рд╡ाрд▓ा value।

3.2 Salvage Value

Useful materials (doors, windows, steel) рдХा resale value।

ЁЯУМ MCQ Tip: Scrap value < Salvage value

ЁЯФ╣ 4. Depreciation (рд╣्рд░ाрд╕)

Depreciation property рдХी value рдоें time рдХे рд╕ाрде рд╣ोрдиे рд╡ाрд▓ी рдХрдоी рдХो рдХрд╣рддे рд╣ैं।

ЁЯФ╕ Causes of Depreciation

  • Wear & tear
  • Weather effect
  • Obsolescence
  • Neglect

ЁЯФ╕ Methods of Depreciation

(a) Straight Line Method

Annual depreciation = (Original cost – Scrap value) / Life

(b) Constant Percentage Method

Value reduces by fixed % every year.

(c) Sinking Fund Method

Annual amount deposited to replace asset after its life.

ЁЯУМ UPSSSC JE Favourite: Most accurate method = Sinking fund method

ЁЯФ╣ 5. Sinking Fund

Sinking Fund рд╡рд╣ fund рд╣ै рдЬिрд╕рдоें рд╣рд░ рд╕ाрд▓ рдХुрдЫ рд░ाрд╢ि рдЬрдоा рдХी рдЬाрддी рд╣ै рддाрдХि asset рдХे end of life рдкрд░ replacement рд╣ो рд╕рдХे।

ЁЯФ╕ Formula

Annual Sinking Fund = (Replacement cost – Scrap value) × i / ((1+i)тБ┐ – 1)

Where, i = rate of interest n = life of building (years)

ЁЯУМ MCQ Tip: Sinking fund considers compound interest

✅ PART–6 Complete
✔ Valuation basics ✔ Market, Book, Capitalised value ✔ Scrap & Salvage value ✔ Depreciation methods ✔ Sinking fund with formula ЁЯСЙ Next: PART–7 • Contract Management • Types of Contracts • Tender, EMD, Security Deposit • Arbitration (PYQ)

2.8 Construction Estimation, Costing & Valuation
PART–7 : Contract Management & Tendering

Exam Focus: Contract Management рд╕े UPSSSC JE рдоें Direct Theory + MCQ рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Contract – Introduction

Contract рдПрдХ legal agreement рд╣ै рдЬो рджो рдпा рдЕрдзिрдХ parties рдХे рдмीрдЪ рдХिрд╕ी work рдХो рдХрд░рдиे рдпा рди рдХрд░рдиे рдХे рд▓िрдП рдмрдиाрдпा рдЬाрддा рд╣ै।

ЁЯФ╕ Essential Elements of Contract

  • Offer
  • Acceptance
  • Lawful consideration
  • Competent parties
  • Lawful object

ЁЯУМ MCQ: Contract becomes valid only when all essentials are present.

ЁЯФ╣ 2. Types of Contracts

2.1 Lump Sum Contract

  • Fixed total cost
  • Suitable when drawings complete рд╣ों

2.2 Item Rate Contract

  • Payment item-wise
  • Most common in government works

2.3 Percentage Rate Contract

  • Rates based on SOR ± percentage

2.4 Cost Plus Contract

  • Actual cost + fixed percentage profit

2.5 Labour Contract

  • Contractor supplies only labour

ЁЯУМ Exam Favourite: Most commonly used contract = Item rate contract

ЁЯФ╣ 3. Tender (рдиिрд╡िрджा)

Tender рдПрдХ formal offer рд╣ै рдЬो contractor рдж्рд╡ाрд░ा department рдХो рджिрдпा рдЬाрддा рд╣ै।

ЁЯФ╕ Types of Tender

  • Open Tender
  • Limited Tender
  • Single Tender
  • Negotiated Tender

ЁЯУМ MCQ: Open tender ensures maximum competition.

ЁЯФ╣ 4. Earnest Money Deposit (EMD)

EMD рд╡рд╣ рд░ाрд╢ि рд╣ै рдЬो contractor tender рдХे рд╕ाрде рдЬрдоा рдХрд░рддा рд╣ै।

  • Ensures seriousness of bidder
  • Generally 1–2% of estimated cost

ЁЯФ╕ Security Deposit

  • Deducted from running bills
  • Generally 5–10% of contract value

ЁЯФ╣ 5. Arbitration

Arbitration dispute resolution рдХा legal рддрд░ीрдХा рд╣ै рдЬिрд╕рдоें third party (Arbitrator) decision рджेрддा рд╣ै।

  • Avoids court litigation
  • Time-saving & economical

ЁЯУМ UPSSSC JE MCQ: Arbitration avoids court cases.

✅ PART–7 Complete
✔ Contract basics ✔ Types of contracts ✔ Tendering process ✔ EMD & Security deposit ✔ Arbitration ЁЯСЙ Next: PART–8 • Extra Items & Deviation • Escalation clause • Measurement Book (MB) • Completion Certificate

2.8 Construction Estimation, Costing & Valuation
PART–8 : Extra Item, MB & Bills

Exam Focus: PART–8 рд╕े Direct Definition + MCQ + Practical Questions рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Extra Item (рдЕрддिрд░िрдХ्рдд рдордж)

Extra Item рд╡рд╣ work рд╣ै рдЬो original agreement рдоें рд╢ाрдоिрд▓ рдирд╣ीं рд╣ोрддा рд▓ेрдХिрди site condition рдХे рдХाрд░рдг рдХрд░рдиा рдЖрд╡рд╢्рдпрдХ рд╣ो рдЬाрддा рд╣ै।

ЁЯФ╕ Characteristics

  • Not included in original BOQ
  • Requires approval of competent authority
  • Paid at analysed rate

ЁЯУМ MCQ: Extra items are paid on the basis of rate analysis.

ЁЯФ╣ 2. Deviation (рд╡िрдЪрд▓рди)

Deviation рдХा рдЕрд░्рде рд╣ै sanctioned quantity рдпा specification рдоें рдкрд░िрд╡рд░्рддрди।

ЁЯФ╕ Types of Deviation

  • Positive deviation – Quantity increase
  • Negative deviation – Quantity decrease

ЁЯУМ UPSSSC JE Point: Deviation beyond permissible limit requires revised sanction.

ЁЯФ╣ 3. Escalation Clause

Escalation Clause contract рдоें рд╡рд╣ provision рд╣ै рдЬो material, labour рдпा fuel рдХी price рдмрдв़рдиे рдкрд░ contractor рдХो compensation рджेрддा рд╣ै।

ЁЯФ╕ Purpose

  • Protection against inflation
  • Long duration projects

ЁЯУМ Exam MCQ: Escalation clause protects contractor against price rise.

ЁЯФ╣ 4. Measurement Book (MB)

Measurement Book рд╡рд╣ official record рд╣ै рдЬिрд╕рдоें site рдкрд░ execute рдХिрдП рдЧрдП рдХाрдо рдХी measurement рджрд░्рдЬ рдХी рдЬाрддी рд╣ै।

ЁЯФ╕ Importance

  • Basis of payment
  • Permanent official record
  • Audit reference

ЁЯУМ Exam Line: MB is the most important financial document in construction.

ЁЯФ╣ 5. Types of Bills

5.1 Running Account Bill (RA Bill)

  • Interim payment
  • Paid periodically

5.2 Final Bill

  • Prepared after completion of work
  • Includes all adjustments

ЁЯФ╣ 6. Completion Certificate

Completion certificate certify рдХрд░рддा рд╣ै рдХि work as per specification & agreement complete рд╣ो рдЪुрдХा рд╣ै।

ЁЯУМ Issued after final inspection of work.

✅ PART–8 Complete
✔ Extra item & deviation ✔ Escalation clause ✔ Measurement Book ✔ RA Bill, Final Bill ✔ Completion certificate ЁЯСЙ Next: PART–9 • Specification (General & Detailed) • Schedule of Rates (SOR) • Contingencies & Work Charged Establishment

2.8 Construction Estimation, Costing & Valuation
PART–9 : Specifications, SOR & Contingencies

Exam Focus: PART–9 рд╕े UPSSSC JE рдоें Direct Theory + MCQ рдмрд╣ुрдд рдкूрдЫे рдЬाрддे рд╣ैं।

ЁЯФ╣ 1. Specification (рд╡िрд╢ेрд╖ рд╡िрд╡рд░рдг) – Introduction

Specification рд╡рд╣ written document рд╣ै рдЬिрд╕рдоें materials рдХी quality, workmanship, method of execution рдФрд░ standards clearly define рдХिрдП рдЬाрддे рд╣ैं।

ЁЯУМ Exam Line: Specification defines the quality of work.

ЁЯФ╕ Importance of Specification

  • Quality control
  • Uniformity of work
  • Dispute avoidance
  • Basis of rate analysis

ЁЯФ╣ 2. Types of Specification

2.1 General Specification

  • Overall description of work
  • Broad guidelines only
  • Used in preliminary estimate

2.2 Detailed Specification

  • Item-wise detailed description
  • Material, proportion, method included
  • Used in detailed estimate & contract

ЁЯУМ Exam Favourite: Detailed specification is used for rate analysis.

ЁЯФ╣ 3. Schedule of Rates (SOR)

SOR рд╡рд╣ document рд╣ै рдЬिрд╕рдоें standard rates of construction items рджिрдП рдЬाрддे рд╣ैं।

ЁЯФ╕ Prepared by

  • CPWD
  • State PWD
  • Other government departments

ЁЯФ╕ Purpose of SOR

  • Uniformity in rates
  • Preparation of estimates
  • Basis of tendering

ЁЯУМ MCQ: SOR ensures uniform rates in a region.

ЁЯФ╣ 4. Contingencies

Contingencies рд╡рд╣ provision рд╣ै рдЬो unexpected items рдХो cover рдХрд░рдиे рдХे рд▓िрдП рд░рдЦा рдЬाрддा рд╣ै।

  • Generally 3–5% of estimated cost
  • Used only with approval

ЁЯУМ Exam MCQ: Contingencies are provided for unforeseen expenses.

ЁЯФ╣ 5. Work-Charged Establishment

Work-charged establishment рдоें рд╡рд╣ staff рд╢ाрдоिрд▓ рд╣ोрддा рд╣ै рдЬो project duration рддрдХ рд╣ी employed рд░рд╣рддा рд╣ै।

  • Supervisors
  • Clerks
  • Watchmen

ЁЯУМ Exam Line: Work-charged staff is paid from project cost.

✅ PART–9 Complete
✔ Specification (General & Detailed) ✔ Schedule of Rates (SOR) ✔ Contingencies ✔ Work-charged establishment ЁЯСЙ Next: PART–10 (FINAL) • Complete Revision Notes • One-liner PYQ points • Exam-oriented Summary & MCQs

2.8 Construction Estimation, Costing & Valuation
PART–10 (FINAL) : Complete Revision & PYQ One-liners

Exam Focus: рдпрд╣ рднाрдЧ Last-Day Revision рдХे рд▓िрдП рдмрдиाрдпा рдЧрдпा рд╣ै – Direct MCQ recall.

ЁЯФ╣ A. Ultra-Quick Revision (Key Facts)

  • Most accurate estimation method = Long wall – Short wall
  • Fastest estimation method = Centre line method
  • Plinth area method used for = Preliminary estimate
  • Cubical content method is more accurate than plinth area
  • Detailed estimate prepared after = Complete drawings
  • BOQ ensures = Transparent tendering
  • Earthwork, concrete, brickwork measured in =
  • Plastering & painting measured in =
  • Formwork measured in =
  • Steel reinforcement measured in = kg / tonne

ЁЯФ╣ B. Rate Analysis – One-liners

  • Dry volume factor for concrete = 1.54
  • Out-turn means = Work done per labour per day
  • Lead = Horizontal transport distance
  • Lift = Vertical transport distance
  • T&P charges generally = 1–2%
  • Overheads generally = 2–5%
  • Contractor’s profit = 8–10%
  • Brickwork bricks per m³ ≈ 500 Nos.
  • Extra items paid at = Analysed rate

ЁЯФ╣ C. Valuation – One-liners (High Scoring)

  • Valuation finds = Present worth of property
  • Market value depends on = Demand, location & utility
  • Book value = Original cost – Depreciation
  • Capitalised value = Net income / Rate of interest
  • Scrap value < Salvage value
  • Depreciation = Loss of value with time
  • Most accurate depreciation method = Sinking fund
  • Sinking fund considers = Compound interest

ЁЯФ╣ D. Contract & Tender – One-liners

  • Most common contract = Item rate contract
  • Open tender ensures = Maximum competition
  • EMD ensures = Seriousness of bidder
  • EMD amount ≈ 1–2% of estimated cost
  • Security deposit ≈ 5–10% of contract value
  • Arbitration avoids = Court litigation
  • Escalation clause protects against = Price rise

ЁЯФ╣ E. MB, Bills & Records

  • MB = Most important financial record
  • RA bill = Interim payment
  • Final bill prepared after = Completion of work
  • Completion certificate issued after = Final inspection

ЁЯФ╣ F. Specification & SOR – One-liners

  • Specification defines = Quality of work
  • Detailed specification used for = Rate analysis
  • SOR prepared by = CPWD / State PWD
  • SOR ensures = Uniform rates
  • Contingencies provided for = Unforeseen items
  • Contingencies ≈ 3–5%
  • Work-charged staff paid from = Project cost

ЁЯФ╣ G. Expected MCQs (Last-Minute)

  1. Most accurate method of estimation is — Long wall–Short wall
  2. Formwork is measured in —
  3. Dry volume factor for PCC is — 1.54
  4. Extra items are paid at — Analysed rate
  5. EMD is taken to ensure — Seriousness of bidder
  6. Book value equals — Original cost – Depreciation
  7. Most accurate depreciation method — Sinking fund
  8. MB is used for — Recording measurements
  9. Open tender ensures — Maximum competition
  10. Contingencies cover — Unforeseen expenditure
ЁЯОп CHAPTER STATUS: 100% COMPLETE
✔ Part 1–10 Covered ✔ Theory + Numericals + PYQ One-liners ✔ Last-day revision ready for UPSSSC JE ЁЯСЙ Next optional add-ons: • Only MCQs (200+)Only PYQ (Year-wise)Printable PDFSEO Title + Meta + Thumbnail

SET-1 : Estimation Basics (Q1–25)

Q1. Estimation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Advance calculation of project cost
Q2. Estimation рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Planning and budget control
Q3. рд╕рдмрд╕े accurate estimation method рдХौрди рд╕ा рд╣ै?
Long wall – Short wall method
Q4. рд╕рдмрд╕े рддेрдЬ estimation method рдХौрди рд╕ा рд╣ै?
Centre line method
Q5. Preliminary estimate рдХिрд╕рдХे рд▓िрдП рдмрдиाрдпा рдЬाрддा рд╣ै?
Administrative approval рдХे рд▓िрдП
Q6. Detailed estimate рдХिрд╕рдХे рд▓िрдП рдмрдиाрдпा рдЬाрддा рд╣ै?
Technical sanction рдХे рд▓िрдП
Q7. Detailed estimate рдХрдм prepare рдХिрдпा рдЬाрддा рд╣ै?
Complete drawings рдХे рдмाрдж
Q8. Plinth area method рдХिрд╕ estimate рдоें рдЙрдкрдпोрдЧ рд╣ोрддा рд╣ै?
Preliminary / rough estimate
Q9. Cubical content method рдХिрд╕рд╕े рдЕрдзिрдХ accurate рд╣ै?
Plinth area method рд╕े
Q10. BOQ рдХा full form рдХ्рдпा рд╣ै?
Bill of Quantities
Q11. BOQ рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Transparent tendering
Q12. Measurement rules рдХिрд╕ code рдоें рджिрдП рдЧрдП рд╣ैं?
IS 1200
Q13. Earthwork рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Cubic metre (m³)
Q14. Brickwork рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Cubic metre (m³)
Q15. Concrete рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Cubic metre (m³)
Q16. Plastering рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Square metre (m²)
Q17. Painting рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Square metre (m²)
Q18. Formwork рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Square metre (m²)
Q19. Steel reinforcement рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
kg рдпा tonne
Q20. 0.1 m² рд╕े рдЫोрдЯे opening рдкрд░ deduction рд╣ोрддा рд╣ै?
рдирд╣ीं (No deduction)
Q21. Centre line method рдХिрд╕ building рдХे рд▓िрдП suitable рд╣ै?
Symmetrical building
Q22. Long wall method рдХिрд╕ building рдХे рд▓िрдП suitable рд╣ै?
Complex building
Q23. Volume рдиिрдХाрд▓рдиे рдХा formula рдХ्рдпा рд╣ै?
Length × Breadth × Depth
Q24. DPC рдХिрд╕ unit рдоें measure рд╣ोрддी рд╣ै?
Square metre (m²)
Q25. Estimation civil engineering рдХा рдХ्рдпा рд╣ै?
Backbone

SET–2 : Estimation & Measurement (Q26–Q50)

Q26. White washing рдХिрд╕ unit рдоें measure рдХी рдЬाрддी рд╣ै?
Square metre (m²)
Q27. Flooring рд╕ाрдоाрди्рдпрддः рдХिрд╕ unit рдоें measure рд╣ोрддी рд╣ै?
Square metre (m²)
Q28. RCC work рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Cubic metre (m³)
Q29. Formwork estimation рдоें рдХिрд╕ area рдХो consider рдХिрдпा рдЬाрддा рд╣ै?
Contact area of concrete surface
Q30. Staircase area рдХिрд╕ area рдоें рд╢ाрдоिрд▓ рд╣ोрддा рд╣ै?
Plinth area
Q31. Courtyard рдХिрд╕ area рд╕े exclude рдХिрдпा рдЬाрддा рд╣ै?
Plinth area
Q32. Carpet area рдоें рдХ्рдпा include рдирд╣ीं рд╣ोрддा?
Wall thickness
Q33. Built-up area, carpet area рд╕े рдХैрд╕ा рд╣ोрддा рд╣ै?
Greater than carpet area
Q34. Abstract of cost рдоें рдХ्рдпा рджрд░्рд╢ाрдпा рдЬाрддा рд╣ै?
Total estimated cost
Q35. Estimate рдХे рд╕ाрде рдХौрди-рд╕े documents attach рд╣ोрддे рд╣ैं?
Drawings & specifications
Q36. Revised estimate рдХрдм рдмрдиाрдпा рдЬाрддा рд╣ै?
When cost exceeds sanctioned limit
Q37. Supplementary estimate рдХ्рдпों рдмрдиाрдпा рдЬाрддा рд╣ै?
For additional works
Q38. Annual repair estimate рдХिрд╕рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Routine maintenance works
Q39. Measurement Book (MB) рдХ्рдпा рд╣ै?
Official record of measurements
Q40. MB рдХा рдЙрдкрдпोрдЧ рдХिрд╕рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Payment of contractor
Q41. Measurement рд╣рдоेрд╢ा рдХिрд╕рдоें record рдХी рдЬाрддी рд╣ै?
Measurement Book
Q42. MB рдоें correction allowed рд╣ोрддी рд╣ै?
No, only proper attestation allowed
Q43. Running Account Bill (RA Bill) рдХ्рдпा рд╣ै?
Interim payment bill
Q44. Final bill рдХрдм prepared рдХिрдпा рдЬाрддा рд╣ै?
After completion of work
Q45. Completion certificate рдХрдм issue рдХिрдпा рдЬाрддा рд╣ै?
After final inspection
Q46. Estimate рдХी validity рдХैрд╕ी рд╣ोрддी рд╣ै?
Limited period
Q47. Measurement unit of length рдХ्рдпा рд╣ै?
Running metre
Q48. Estimation error рд╕े рдХ्рдпा рд╣ोрддा рд╣ै?
Cost overrun
Q49. Estimation рдХिрд╕ stage рдкрд░ рд╕рдмрд╕े рдЬ़рд░ूрд░ी рд╣ै?
Planning stage
Q50. Estimation & costing рдХा ultimate aim рдХ्рдпा рд╣ै?
Financial control

SET–3 : Rate Analysis (Q51–Q75)

Q51. Rate analysis рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Unit cost of an item determine рдХрд░рдиा
Q52. Rate analysis рдХिрд╕ quantity рдХे рд▓िрдП рдХिрдпा рдЬाрддा рд╣ै?
One unit of work
Q53. Rate analysis рдХे рдоुрдЦ्рдп components рдХौрди-рдХौрди рд╕े рд╣ैं?
Material, Labour, T&P, Overheads, Profit
Q54. Concrete рдХे рд▓िрдП dry volume factor рдХिрддрдиा рд╣ोрддा рд╣ै?
1.54
Q55. Mortar (brickwork) рдХे рд▓िрдП dry volume factor рдХिрддрдиा рдоाрдиा рдЬाрддा рд╣ै?
1.30 (approx.)
Q56. Lead рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Horizontal transport distance
Q57. Lift рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Vertical transport distance
Q58. Out-turn рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Work done by labour per day
Q59. Contractor рдХा standard profit рдХिрддрдиा рдоाрдиा рдЬाрддा рд╣ै?
8–10%
Q60. Overheads рд╕ाрдоाрди्рдпрддः рдХिрддрдиे рдк्рд░рддिрд╢рдд рд▓िрдП рдЬाрддे рд╣ैं?
2–5%
Q61. Tools & Plants (T&P) charges рд╕ाрдоाрди्рдпрддः рдХिрддрдиे рдк्рд░рддिрд╢рдд рд╣ोрддे рд╣ैं?
1–2%
Q62. 1 m³ brick masonry рдоें рд▓рдЧрднрдЧ рдХिрддрдиी рдИंрдЯें рд▓рдЧрддी рд╣ैं?
≈ 500 bricks
Q63. Brick masonry рдХे рд▓िрдП рд╕ाрдоाрди्рдп mortar ratio рдХ्рдпा рд╣ोрддा рд╣ै?
1:6 (cement:sand)
Q64. Cement рдХे рдПрдХ bag рдХा standard volume рдХिрддрдиा рд╣ै?
0.035 m³
Q65. Cement рдХे рдПрдХ bag рдХा standard weight рдХिрддрдиा рд╣ोрддा рд╣ै?
50 kg
Q66. Sand рдХा maximum bulking рд▓рдЧрднрдЧ рдХिрддрдиा рд╣ोрддा рд╣ै?
30%
Q67. Extra item рдХा payment рдХिрд╕ basis рдкрд░ рдХिрдпा рдЬाрддा рд╣ै?
Analysed rate
Q68. Rate analysis рдоें royalty рдХिрд╕ cost рдоें рд╢ाрдоिрд▓ рд╣ोрддी рд╣ै?
Material cost
Q69. Scaffolding charges рдХिрд╕ head рдоें рд╢ाрдоिрд▓ рд╣ोрддे рд╣ैं?
Tools & Plants (T&P)
Q70. Machine mixing рд╕े рдХिрд╕ cost рдоें рдХрдоी рдЖрддी рд╣ै?
Labour cost
Q71. Rate analysis рдХा base document рдХ्рдпा рд╣ोрддा рд╣ै?
Schedule of Rates (SOR)
Q72. Rate analysis region-wise рдЕрд▓рдЧ рдХ्рдпों рд╣ोрддा рд╣ै?
Material & labour rates vary
Q73. Rate analysis рдХिрд╕ contract type рдоें рд╕рдмрд╕े рдЕрдзिрдХ рдЙрдкрдпोрдЧ рд╣ोрддा рд╣ै?
Item rate contract
Q74. Rate analysis рдХा рдоुрдЦ्рдп рд▓ाрдн рдХ्рдпा рд╣ै?
Fair and realistic costing
Q75. Rate analysis рдХिрд╕рдХे рд▓िрдП рдЕрдиिрд╡ाрд░्рдп рд╣ै?
Extra items & tendering

SET–4 : Valuation & Depreciation (Q76–Q100)

Q76. Valuation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Present worth of property determine рдХрд░рдиा
Q77. Market value рдХिрд╕ рдкрд░ рдиिрд░्рднрд░ рдХрд░рддी рд╣ै?
Demand, location & utility
Q78. Book value рдХिрд╕рдХे рдмрд░ाрдмрд░ рд╣ोрддी рд╣ै?
Original cost – depreciation
Q79. Capitalised value рдХा basic formula рдХ्рдпा рд╣ै?
Net annual income / rate of interest
Q80. Rental value рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Property рд╕े рдоिрд▓рдиे рд╡ाрд▓ा annual rent
Q81. Scrap value рдХ्рдпा рд╣ोрддी рд╣ै?
Demolition рдХे рдмाрдж material рдХी value
Q82. Salvage value рдХ्рдпा рд╣ोрддी рд╣ै?
Reusable materials рдХी resale value
Q83. Scrap value рдФрд░ salvage value рдоें рдХौрди-рд╕ी рдЕрдзिрдХ рд╣ोрддी рд╣ै?
Salvage value
Q84. Depreciation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Time рдХे рд╕ाрде value рдоें рдХрдоी
Q85. Depreciation рдХे рдоुрдЦ्рдп рдХाрд░рдг рдХ्рдпा рд╣ैं?
Wear & tear, weather, obsolescence
Q86. Straight line method рдоें depreciation рдХैрд╕ा рд╣ोрддा рд╣ै?
Every year equal amount
Q87. рд╕рдмрд╕े accurate depreciation method рдХौрди-рд╕ा рд╣ै?
Sinking fund method
Q88. Sinking fund method рдХिрд╕ principle рдкрд░ based рд╣ै?
Compound interest
Q89. Depreciation рдХिрд╕ property рдкрд░ рд▓ाрдЧू рдирд╣ीं рд╣ोрддा?
Land
Q90. Insurance value рдоें рдХ्рдпा exclude рдХिрдпा рдЬाрддा рд╣ै?
Land cost
Q91. Distress value рдХ्рдпा рджрд░्рд╢ाрддी рд╣ै?
Forced sale value
Q92. Capitalised value рдХा рдЙрдкрдпोрдЧ рдХрд╣ाँ рд╣ोрддा рд╣ै?
Income-producing property
Q93. Net annual income рдХैрд╕े рдиिрдХाрд▓ी рдЬाрддी рд╣ै?
Gross income – outgoings
Q94. Outgoings рдоें рдХ्рдпा рд╢ाрдоिрд▓ рд╣ोрддे рд╣ैं?
Taxes, repairs & maintenance
Q95. RCC building рдХी average life рдХिрддрдиी рдоाрдиी рдЬाрддी рд╣ै?
60–80 years
Q96. Valuation рдХी рдЖрд╡рд╢्рдпрдХрддा рдХ्рдпों рд╣ोрддी рд╣ै?
Sale, mortgage, tax & insurance
Q97. Land value рд╕ाрдоाрди्рдпрддः рд╕рдордп рдХे рд╕ाрде рдХ्рдпा рдХрд░рддी рд╣ै?
Appreciate (increase)
Q98. Valuation report рдХौрди рддैрдпाрд░ рдХрд░рддा рд╣ै?
Authorized engineer / valuer
Q99. Capitalised value interest rate рдХрдо рд╣ोрдиे рдкрд░ рдХ्рдпा рд╣ोрдЧी?
Higher
Q100. Valuation рдХो рдХ्рдпा рдХрд╣ा рдЬाрддा рд╣ै?
Art as well as science

SET–5 : Contracts & Tender (Q101–Q125)

Q101. Contract рдХ्рдпा рд╣ै?
Two or more parties рдХे рдмीрдЪ legal agreement
Q102. Contract рдХे essential elements рдХौрди-рдХौрди рд╕े рд╣ैं?
Offer, Acceptance, Consideration, Competent parties
Q103. Government works рдоें рд╕рдмрд╕े common contract рдХौрди-рд╕ा рд╣ै?
Item rate contract
Q104. Lump sum contract рдХрдм suitable рд╣ोрддा рд╣ै?
When drawings & specifications are complete
Q105. Percentage rate contract рдХिрд╕ рдкрд░ based рд╣ोрддा рд╣ै?
SOR ± quoted percentage
Q106. Cost plus contract рдоें contractor рдХो рдХ्рдпा рдоिрд▓рддा рд╣ै?
Actual cost + fixed percentage profit
Q107. Labour contract рдоें contractor рдХ्рдпा supply рдХрд░рддा рд╣ै?
Only labour
Q108. Tender рдХ्рдпा рд╣ोрддा рд╣ै?
Formal offer to execute work
Q109. Open tender рдХा рдоुрдЦ्рдп рд▓ाрдн рдХ्рдпा рд╣ै?
Maximum competition
Q110. Limited tender рдХिрди्рд╣ें invite рдХिрдпा рдЬाрддा рд╣ै?
Selected contractors
Q111. Single tender рдХрдм рдЕрдкрдиाрдпा рдЬाрддा рд╣ै?
Emergency / proprietary works
Q112. Negotiated tender рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Rates decided by mutual discussion
Q113. EMD рдХा full form рдХ्рдпा рд╣ै?
Earnest Money Deposit
Q114. EMD рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Ensure seriousness of bidder
Q115. EMD рд╕ाрдоाрди्рдпрддः рдХिрддрдиे рдк्рд░рддिрд╢рдд рд╣ोрддी рд╣ै?
1–2% of estimated cost
Q116. Security Deposit (SD) рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Ensure proper performance of work
Q117. Security Deposit рд╕ाрдоाрди्рдпрддः рдХिрддрдиा рд╣ोрддा рд╣ै?
5–10% of contract value
Q118. Agreement рдХрдм signed рдХिрдпा рдЬाрддा рд╣ै?
After acceptance of tender
Q119. Contract document рдоें рдХ्рдпा-рдХ्рдпा рд╢ाрдоिрд▓ рд╣ोрддे рд╣ैं?
Drawings, BOQ, specifications & conditions
Q120. Tender validity period рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Time during which tender remains open
Q121. Lowest tender рд╣рдоेрд╢ा accept рдХिрдпा рдЬाрддा рд╣ै?
No, not always
Q122. Tender notice рдХрд╣ाँ publish рдХिрдпा рдЬाрддा рд╣ै?
Newspaper / e-portal
Q123. Agreement рдХिрд╕ рдкрд░ signed рд╣ोрддी рд╣ै?
Stamp paper
Q124. Contract рдХिрд╕ act рдХे рдЕрдиुрд╕ाрд░ governed рд╣ोрддा рд╣ै?
Indian Contract Act
Q125. Contract documents рдХी legal nature рдХ्рдпा рд╣ोрддी рд╣ै?
Legally binding

SET–6 : Arbitration, Escalation & Extra Items (Q126–Q150)

Q126. Arbitration рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Dispute resolution by third party
Q127. Arbitration рдХा рдоुрдЦ्рдп рд▓ाрдн рдХ्рдпा рд╣ै?
Avoids court litigation
Q128. Arbitrator рдХौрди рд╣ोрддा рд╣ै?
Neutral third party
Q129. Arbitration award рдХी nature рдХैрд╕ी рд╣ोрддी рд╣ै?
Binding on both parties
Q130. Escalation clause рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Compensation against price rise
Q131. Escalation clause рдХिрди projects рдоें рджी рдЬाрддी рд╣ै?
Long duration projects
Q132. Escalation clause рдХिрди costs рдкрд░ рд▓ाрдЧू рд╣ोрддी рд╣ै?
Material, labour & fuel
Q133. Escalation calculation рдХिрд╕ basis рдкрд░ рд╣ोрддी рд╣ै?
Price index
Q134. Extra item рдХ्рдпा рд╣ोрддा рд╣ै?
Item not included in original BOQ
Q135. Extra item рдХ्рдпों arise рд╣ोрддा рд╣ै?
Site condition / design change
Q136. Extra item рдХा payment рдХिрд╕ basis рдкрд░ рдХिрдпा рдЬाрддा рд╣ै?
Analysed rate
Q137. Extra item рдХे рд▓िрдП approval рдХिрд╕рд╕े рд▓िрдпा рдЬाрддा рд╣ै?
Competent authority
Q138. Deviation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Change in quantity or specification
Q139. Positive deviation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Increase in quantity
Q140. Negative deviation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Decrease in quantity
Q141. Deviation limit рд╕े рдЕрдзिрдХ рд╣ोрдиे рдкрд░ рдХ्рдпा рдЖрд╡рд╢्рдпрдХ рд╣ै?
Revised sanction
Q142. Measurement Book (MB) рдХा full form рдХ्рдпा рд╣ै?
Measurement Book
Q143. MB рдХा рдЙрдкрдпोрдЧ рдХिрд╕ purpose рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Basis of payment
Q144. MB рдХी nature рдХैрд╕ी рд╣ोрддी рд╣ै?
Permanent official record
Q145. Running Account Bill (RA Bill) рдХ्рдпा рд╣ै?
Interim payment bill
Q146. Final bill рдХрдм prepared рдХिрдпा рдЬाрддा рд╣ै?
After completion of work
Q147. Completion certificate рдХрдм issue рдХिрдпा рдЬाрддा рд╣ै?
After final inspection
Q148. Completion certificate рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Certify work as per agreement
Q149. Security deposit refund рдХрдм рдХिрдпा рдЬाрддा рд╣ै?
After defect liability period
Q150. Extra items & deviation рдХिрд╕ stage рдкрд░ рдЕрдзिрдХ рдЖрддे рд╣ैं?
Execution stage

SET–7 : Specifications, SOR & Contingencies (Q151–Q175)

Q151. Specification рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Quality, material & workmanship рдХा written description
Q152. Specification рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Quality control рдФрд░ disputes avoid рдХрд░рдиा
Q153. General specification рдХ्рдпा рдмрддाрддी рд╣ै?
Work рдХा overall description
Q154. Detailed specification рдХा рдЙрдкрдпोрдЧ рдХрд╣ाँ рд╣ोрддा рд╣ै?
Rate analysis рдФрд░ contract documents рдоें
Q155. Detailed specification рдоें рдХ्рдпा-рдХ्рдпा рд╢ाрдоिрд▓ рд╣ोрддा рд╣ै?
Material, proportion, method & workmanship
Q156. Schedule of Rates (SOR) рдХ्рдпा рд╣ै?
Standard rates рдХा approved document
Q157. SOR рдХौрди prepare рдХрд░рддा рд╣ै?
PWD / CPWD / State departments
Q158. SOR рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Uniformity in rates ensure рдХрд░рдиा
Q159. SOR рдХिрд╕ basis рдкрд░ revise рдХिрдпा рдЬाрддा рд╣ै?
Market rates & wage variation
Q160. SOR рдХा рдЙрдкрдпोрдЧ рдХिрд╕рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Estimate preparation & tendering
Q161. Contingencies рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Unforeseen expenses рдХे рд▓िрдП provision
Q162. Contingencies рд╕ाрдоाрди्рдпрддः рдХिрддрдиे рдк्рд░рддिрд╢рдд рд░рдЦी рдЬाрддी рд╣ैं?
3–5% of estimated cost
Q163. Contingencies рдХा рдЙрдкрдпोрдЧ рдХिрд╕рдХे рд▓िрдП рдирд╣ीं рдХिрдпा рдЬाрддा?
Major scope changes
Q164. Work-charged establishment рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Project duration рддрдХ employed staff
Q165. Work-charged staff рдХा salary рдХिрд╕рд╕े pay рд╣ोрддा рд╣ै?
Project cost
Q166. Abstract of cost рдоें рдХ्рдпा рджिрдЦाрдпा рдЬाрддा рд╣ै?
Total estimated cost summary
Q167. Estimate рдХी validity рдХ्рдпों limited рд╣ोрддी рд╣ै?
Market rates change рд╣ोрдиे рдХे рдХाрд░рдг
Q168. Detailed estimate рдХे рд╕ाрде рдХौрди-рд╕ा annexure рдЬрд░ूрд░ी рд╣ै?
BOQ
Q169. Specification contract рдХा рдХौрди-рд╕ा рднाрдЧ рд╣ै?
Essential part
Q170. SOR rates рдоें рдХ्рдпा-рдХ्рдпा included рд╣ोрддे рд╣ैं?
Material, labour & carriage
Q171. Contingencies рдХा approval рдХिрд╕рд╕े рд▓िрдпा рдЬाрддा рд╣ै?
Competent authority
Q172. SOR region-wise рдЕрд▓рдЧ рдХ्рдпों рд╣ोрддी рд╣ै?
Local material & labour rates differ
Q173. Specification disputes рдХो рдХैрд╕े reduce рдХрд░рддी рд╣ै?
Clear quality & method definition рд╕े
Q174. Work-charged establishment permanent рд╣ोрддा рд╣ै?
No, project-based only
Q175. Specification рдХा ultimate aim рдХ्рдпा рд╣ै?
Quality work ensure рдХрд░рдиा

SET–8 : MB, Bills & Completion (Q176–Q200)

Q176. Measurement Book (MB) рдХ्рдпा рд╣ै?
Executed work рдХी official measurement record
Q177. MB рдХो рд╕рдмрд╕े рдорд╣рдд्рд╡рдкूрд░्рдг document рдХ्рдпों рдоाрдиा рдЬाрддा рд╣ै?
Payment рдЗрд╕ी рдХे рдЖрдзाрд░ рдкрд░ рд╣ोрддा рд╣ै
Q178. MB рдоें measurement рдХौрди record рдХрд░рддा рд╣ै?
Engineer / authorized officer
Q179. MB рдоें entry рдХिрд╕рд╕े рдХी рдЬाрддी рд╣ै?
Ink (permanent)
Q180. MB рдоें correction рдХैрд╕े рдХी рдЬाрддी рд╣ै?
Proper attestation рдХे рд╕ाрде
Q181. Running Account Bill (RA Bill) рдХ्рдпा рд╣ै?
Interim payment bill
Q182. RA Bill рдХिрд╕ interval рдкрд░ prepare рдХिрдпा рдЬाрддा рд╣ै?
Periodically during execution
Q183. RA Bill рдоें рдХ्рдпा-рдХ्рдпा deduct рдХिрдпा рдЬाрддा рд╣ै?
Security deposit & other recoveries
Q184. Final Bill рдХрдм prepare рдХिрдпा рдЬाрддा рд╣ै?
After completion of work
Q185. Final Bill рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Clear all dues of contractor
Q186. Completion Certificate рдХ्рдпा рджрд░्рд╢ाрддा рд╣ै?
Work completed as per agreement
Q187. Completion Certificate рдХрдм issue рдХिрдпा рдЬाрддा рд╣ै?
After final inspection
Q188. Completion Certificate рдХिрд╕рдХे рдж्рд╡ाрд░ा issue рдХिрдпा рдЬाрддा рд╣ै?
Engineer-in-charge
Q189. Defect liability period рдХрдм start рд╣ोрддी рд╣ै?
After completion of work
Q190. Security deposit refund рдХрдм рдХिрдпा рдЬाрддा рд╣ै?
After defect liability period
Q191. Final measurement рдХрд╣ाँ record рд╣ोрддी рд╣ै?
Measurement Book
Q192. MB audit рдХे рд▓िрдП рдХ्рдпों рдЖрд╡рд╢्рдпрдХ рд╣ै?
Permanent official record рд╣ोрдиे рдХे рдХाрд░рдг
Q193. Completion рдХे рдмाрдж рдХौрди-рд╕ा bill final рдоाрдиा рдЬाрддा рд╣ै?
Final Bill
Q194. RA Bill рдФрд░ Final Bill рдоें рдоुрдЦ्рдп рдЕंрддрд░ рдХ्рдпा рд╣ै?
RA = interim, Final = last payment
Q195. Completion Certificate рдХे рдмिрдиा рдХ्рдпा payment рд╣ो рд╕рдХрддी рд╣ै?
No, final payment рдирд╣ीं
Q196. MB рдХिрд╕ category рдХा document рд╣ै?
Financial & technical
Q197. Contractor рдХो final payment рдХрдм рдоिрд▓рддा рд╣ै?
After Final Bill approval
Q198. Completion Certificate issue рдХрд░рдиे рд╕े рдкрд╣рд▓े рдХ्рдпा рдХिрдпा рдЬाрддा рд╣ै?
Final inspection
Q199. Measurement рдоें рдЧрд▓рддी рдХा рд╕рдмрд╕े рдмрдб़ा risk рдХ्рдпा рд╣ै?
Wrong payment
Q200. MB, Bills & Completion рдХिрд╕ stage рд╕े рд╕ंрдмंрдзिрдд рд╣ैं?
Execution & closing stage

SET–9 : Mixed Revision & PYQ (Q201–Q225)

Q201. Preliminary estimate рдХिрд╕ approval рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Administrative approval
Q202. Detailed estimate рдХिрд╕ approval рдХे рд▓िрдП рд╣ोрддा рд╣ै?
Technical sanction
Q203. Centre line method рдХा рдоुрдЦ्рдп advantage рдХ्рдпा рд╣ै?
Fast & easy quantity calculation
Q204. Long wall–short wall method рдХिрд╕ type рдХे building рдХे рд▓िрдП рдмेрд╣рддрд░ рд╣ै?
Complex / unsymmetrical buildings
Q205. Dry volume factor (PCC) рдХिрддрдиा рдоाрдиा рдЬाрддा рд╣ै?
1.54
Q206. Out-turn рдХा рд╕рд╣ी рдЕрд░्рде рдХ्рдпा рд╣ै?
Work done by a labour per day
Q207. Extra item рдХा рднुрдЧрддाрди рдХिрд╕ rate рдкрд░ рдХिрдпा рдЬाрддा рд╣ै?
Analysed rate
Q208. Revised estimate рдХрдм рдЖрд╡рд╢्рдпрдХ рд╣ो рдЬाрддा рд╣ै?
When sanctioned cost exceeds limit
Q209. Valuation рдоें book value рдХ्рдпा рджрд░्рд╢ाрддी рд╣ै?
Original cost minus depreciation
Q210. Capitalised value рдХिрд╕ property рдХे рд▓िрдП рдЙрдкрдпोрдЧी рд╣ै?
Income generating property
Q211. Depreciation apply рдирд╣ीं рд╣ोрддी рд╣ै?
Land рдкрд░
Q212. Sinking fund method рдХिрд╕ interest рдкрд░ based рд╣ै?
Compound interest
Q213. Market value рдХिрд╕ рдХाрд░рдг рдмрджрд▓рддी рд░рд╣рддी рд╣ै?
Demand & supply changes
Q214. Most commonly used government contract рдХौрди рд╕ा рд╣ै?
Item rate contract
Q215. EMD рдХा рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Ensure seriousness of bidder
Q216. Security deposit рдХрдм return рдХी рдЬाрддी рд╣ै?
After defect liability period
Q217. Arbitration рдХा рдоुрдЦ्рдп рдлाрдпрджा рдХ्рдпा рд╣ै?
Avoid court cases
Q218. Escalation clause рдХिрд╕ risk рд╕े рдмрдЪाрддी рд╣ै?
Price rise risk
Q219. SOR рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Uniform rates ensure рдХрд░рдиा
Q220. Contingencies рдХिрд╕рдХे рд▓िрдП рд░рдЦी рдЬाрддी рд╣ैं?
Unforeseen expenses
Q221. Work-charged staff рдХा payment рдХिрд╕рд╕े рд╣ोрддा рд╣ै?
Project cost
Q222. MB рдХो permanent record рдХ्рдпों рдоाрдиा рдЬाрддा рд╣ै?
Audit & payment reference рдХे рд▓िрдП
Q223. RA Bill рдФрд░ Final Bill рдоें рдЕंрддрд░ рдХ्рдпा рд╣ै?
RA = interim, Final = last payment
Q224. Completion certificate рдХ्рдпों рдЖрд╡рд╢्рдпрдХ рд╣ै?
Final payment рдХे рд▓िрдП
Q225. Estimation, costing & valuation рдХा final aim рдХ्рдпा рд╣ै?
Financial control & economy

SET–10 : Final Mixed Revision (Q226–Q250)

Q226. Plinth area рдоें рдХ्рдпा рд╢ाрдоिрд▓ рд╣ोрддा рд╣ै?
Wall thickness рд╕рд╣िрдд covered area
Q227. Carpet area рдоें рдХ्рдпा exclude рдХिрдпा рдЬाрддा рд╣ै?
Wall thickness
Q228. Built-up area рдХिрд╕рд╕े рдЕрдзिрдХ рд╣ोрддी рд╣ै?
Carpet area
Q229. Detailed estimate рдХा рд╕рдмрд╕े рдорд╣рдд्рд╡рдкूрд░्рдг annexure рдХ्рдпा рд╣ै?
Bill of Quantities (BOQ)
Q230. Measurement rules рдХिрд╕ code рдоें рджिрдП рдЧрдП рд╣ैं?
IS 1200
Q231. Earthwork рдХिрд╕ unit рдоें measure рдХिрдпा рдЬाрддा рд╣ै?
Cubic metre (m³)
Q232. Painting рдФрд░ plastering рдХिрд╕ unit рдоें measure рд╣ोрддी рд╣ै?
Square metre (m²)
Q233. Steel reinforcement рдХिрд╕ unit рдоें рд▓िрдпा рдЬाрддा рд╣ै?
kg рдпा tonne
Q234. Dry volume factor (concrete) рдХिрддрдиा рд╣ोрддा рд╣ै?
1.54
Q235. Contractor profit рд╕ाрдоाрди्рдпрддः рдХिрддрдиा рдоाрдиा рдЬाрддा рд╣ै?
8–10%
Q236. Extra item рдХा payment рдХिрд╕ rate рдкрд░ рдХिрдпा рдЬाрддा рд╣ै?
Analysed rate
Q237. Deviation рдХा рдЕрд░्рде рдХ्рдпा рд╣ै?
Change in quantity or specification
Q238. Valuation рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Present worth of property determine рдХрд░рдиा
Q239. Book value рдХैрд╕े рдиिрдХाрд▓ी рдЬाрддी рд╣ै?
Original cost – depreciation
Q240. Capitalised value рдХिрд╕ рдкрд░ depend рдХрд░рддी рд╣ै?
Net income & rate of interest
Q241. Depreciation apply рдирд╣ीं рд╣ोрддी рд╣ै?
Land рдкрд░
Q242. Most accurate depreciation method рдХौрди-рд╕ा рд╣ै?
Sinking fund method
Q243. Sinking fund method рдХिрд╕ interest рдкрд░ based рд╣ै?
Compound interest
Q244. Most common government contract рдХौрди-рд╕ा рд╣ै?
Item rate contract
Q245. EMD рдХा рдоुрдЦ्рдп рдЙрдж्рджेрд╢्рдп рдХ्рдпा рд╣ै?
Ensure seriousness of bidder
Q246. Arbitration рдХा рд╕рдмрд╕े рдмрдб़ा рд▓ाрдн рдХ्рдпा рд╣ै?
Court case avoid рд╣ोрдиा
Q247. Measurement Book (MB) рдХिрд╕ type рдХा record рд╣ै?
Permanent financial & technical record
Q248. Final bill рдХрдм prepared рдХिрдпा рдЬाрддा рд╣ै?
Completion of work рдХे рдмाрдж
Q249. Completion certificate рдХ्рдпों рдЬрд░ूрд░ी рд╣ै?
Final payment рдХे рд▓िрдП
Q250. Estimation, Costing & Valuation рдХा ultimate aim рдХ्рдпा рд╣ै?
Financial control & economy

Estimation, Costing & Valuation
250 One-Liner – PART-2
UPSSSC JE / SSC JE (Civil)

Use: Ultra-Fast Revision • Last-Day Notes • PYQ Recall Format: One-liner only (No MCQ, No break)

  1. Centre line method fastest estimation method рд╣ै
  2. Long wall–short wall method most accurate рдоाрдиा рдЬाрддा рд╣ै
  3. Plinth area estimate rough cost рдмрддाрддा рд╣ै
  4. Cubical content method height рдХो consider рдХрд░рддा рд╣ै
  5. Preliminary estimate administrative approval рдХे рд▓िрдП рд╣ोрддा рд╣ै
  6. Detailed estimate technical sanction рдХे рд▓िрдП рд╣ोрддा рд╣ै
  7. BOQ tender transparency ensure рдХрд░рддा рд╣ै
  8. IS 1200 measurement rules рджेрддा рд╣ै
  9. Earthwork cubic metre рдоें measure рд╣ोрддा рд╣ै
  10. Brickwork cubic metre рдоें measure рд╣ोрддा рд╣ै
  11. Concrete cubic metre рдоें measure рд╣ोрддा рд╣ै
  12. Plastering square metre рдоें measure рд╣ोрддी рд╣ै
  13. Painting square metre рдоें measure рд╣ोрддी рд╣ै
  14. Formwork square metre рдоें measure рд╣ोрддा рд╣ै
  15. Steel reinforcement kg рдпा tonne рдоें measure рд╣ोрддा рд╣ै
  16. 0.1 m² рд╕े рдЫोрдЯी opening deduct рдирд╣ीं рдХी рдЬाрддी
  17. Symmetrical building рдХे рд▓िрдП centre line method best рд╣ै
  18. Complex building рдХे рд▓िрдП long wall method suitable рд╣ै
  19. Abstract of cost total estimated cost рджिрдЦाрддा рд╣ै
  20. Estimate рдХी validity limited period рдХी рд╣ोрддी рд╣ै
  21. Rate analysis unit cost рдмрддाрддा рд╣ै
  22. Rate analysis one unit work рдХे рд▓िрдП рд╣ोрддा рд╣ै
  23. Dry volume factor (concrete) 1.54 рд╣ोрддा рд╣ै
  24. Dry volume factor (mortar) рд▓рдЧрднрдЧ 1.30 рд╣ोрддा рд╣ै
  25. Lead horizontal distance рдХो рдХрд╣рддे рд╣ैं
  26. Lift vertical distance рдХो рдХрд╣рддे рд╣ैं
  27. Out-turn labour productivity рджрд░्рд╢ाрддा рд╣ै
  28. Contractor profit рд╕ाрдоाрди्рдпрддः 8–10% рд╣ोрддा рд╣ै
  29. Overhead charges 2–5% рд╣ोрддे рд╣ैं
  30. T&P charges рд▓рдЧрднрдЧ 1–2% рд╣ोрддे рд╣ैं
  31. 1 cement bag рдХा weight 50 kg рд╣ोрддा рд╣ै
  32. 1 cement bag рдХा volume 0.035 m³ рд╣ोрддा рд╣ै
  33. 1 m³ brickwork рдоें рд▓рдЧрднрдЧ 500 bricks рд▓рдЧрддी рд╣ैं
  34. Sand рдХा maximum bulking рд▓рдЧрднрдЧ 30% рд╣ोрддा рд╣ै
  35. Royalty material cost рдоें рд╢ाрдоिрд▓ рд╣ोрддी рд╣ै
  36. Scaffolding T&P рдоें рд╢ाрдоिрд▓ рд╣ोрддा рд╣ै
  37. Extra item analysed rate рдкрд░ paid рд╣ोрддा рд╣ै
  38. Rate analysis SOR рдкрд░ based рд╣ोрддा рд╣ै
  39. Machine mixing labour cost рдХрдо рдХрд░рддा рд╣ै
  40. Item rate contract rate analysis рдкрд░ depend рдХрд░рддा рд╣ै
  41. Valuation property рдХी present worth рдмрддाрддी рд╣ै
  42. Market value demand рдФрд░ location рдкрд░ depend рдХрд░рддी рд╣ै
  43. Book value = original cost – depreciation
  44. Capitalised value income property рдХे рд▓िрдП рд╣ोрддी рд╣ै
  45. Capitalised value = net income / interest rate
  46. Rental value annual rent рдХो рдХрд╣рддे рд╣ैं
  47. Scrap value demolition рдХे рдмाрдж рдХी value рд╣ै
  48. Salvage value reusable material рдХी value рд╣ै
  49. Salvage value рд╣рдоेрд╢ा scrap value рд╕े рдЕрдзिрдХ рд╣ोрддी рд╣ै
  50. Depreciation value рдоें gradual loss рд╣ै
  51. Land рдкрд░ depreciation рд▓ाрдЧू рдирд╣ीं рд╣ोрддी
  52. Straight line method equal depreciation рджेрддा рд╣ै
  53. Sinking fund most accurate method рд╣ै
  54. Sinking fund compound interest рдкрд░ based рд╣ोрддा рд╣ै
  55. Insurance value рдоें land cost include рдирд╣ीं рд╣ोрддी
  56. Distress value forced sale рдХो рджрд░्рд╢ाрддी рд╣ै
  57. RCC building life рд▓рдЧрднрдЧ 60–80 years рд╣ोрддी рд╣ै
  58. Net income = gross income – outgoings
  59. Outgoings рдоें tax рдФрд░ maintenance рд╢ाрдоिрд▓ рд╣ैं
  60. Valuation sale, mortgage рдФрд░ tax рдХे рд▓िрдП рдХी рдЬाрддी рд╣ै
  61. Contract legal agreement рд╣ोрддा рд╣ै
  62. Item rate contract рд╕рдмрд╕े common govt contract рд╣ै
  63. Lump sum contract complete drawings рдкрд░ suitable рд╣ै
  64. Percentage rate contract SOR рдкрд░ based рд╣ोрддा рд╣ै
  65. Cost plus contract actual cost + profit рджेрддा рд╣ै
  66. Labour contract рдХेрд╡рд▓ labour supply рдХрд░рддा рд╣ै
  67. Tender formal offer рд╣ोрддा рд╣ै
  68. Open tender maximum competition рджेрддा рд╣ै
  69. Limited tender selected contractors рдХे рд▓िрдП рд╣ोрддा рд╣ै
  70. Single tender emergency work рдоें рд╣ोрддा рд╣ै
  71. Negotiated tender mutual discussion рд╕े рд╣ोрддा рд╣ै
  72. EMD bidder рдХी seriousness check рдХрд░рддा рд╣ै
  73. EMD рд╕ाрдоाрди्рдпрддः 1–2% рд╣ोрддी рд╣ै
  74. Security deposit 5–10% рд╣ोрддा рд╣ै
  75. Agreement tender acceptance рдХे рдмाрдж sign рд╣ोрддी рд╣ै
  76. Contract Indian Contract Act рд╕े governed рд╣ोрддा рд╣ै
  77. Lowest tender рд╣рдоेрд╢ा accept рдирд╣ीं рд╣ोрддा
  78. Arbitration dispute resolution рдХा рддрд░ीрдХा рд╣ै
  79. Arbitration court case avoid рдХрд░рддा рд╣ै
  80. Arbitration award binding рд╣ोрддा рд╣ै
  81. Escalation clause price rise рд╕े protection рджेрддी рд╣ै
  82. Escalation long duration projects рдоें рд╣ोрддी рд╣ै
  83. Extra item BOQ рдоें include рдирд╣ीं рд╣ोрддा
  84. Extra item analysed rate рдкрд░ paid рд╣ोрддा рд╣ै
  85. Deviation quantity change рдХो рдХрд╣рддे рд╣ैं
  86. Positive deviation quantity increase рд╣ै
  87. Negative deviation quantity decrease рд╣ै
  88. Deviation limit cross рд╣ोрдиे рдкрд░ revised sanction рдЪाрд╣िрдП
  89. MB Measurement Book рдХрд╣рд▓ाрддी рд╣ै
  90. MB permanent official record рд╣ोрддी рд╣ै
  91. MB payment рдХा base document рд╣ै
  92. MB рдоें entry ink рд╕े рдХी рдЬाрддी рд╣ै
  93. MB correction proper attestation рд╕े рд╣ोрддी рд╣ै
  94. RA Bill interim payment рд╣ोрддी рд╣ै
  95. Final Bill completion рдХे рдмाрдж рдмрдирддी рд╣ै
  96. Completion certificate final inspection рдХे рдмाрдж рдоिрд▓рддा рд╣ै
  97. Defect liability period completion рдХे рдмाрдж рд╢ुрд░ू рд╣ोрддी рд╣ै
  98. Security deposit defect period рдХे рдмाрдж refund рд╣ोрддी рд╣ै
  99. Final bill рд╕рднी dues clear рдХрд░рддी рд╣ै
  100. Specification quality of work define рдХрд░рддी рд╣ै
  101. General specification overall description рджेрддी рд╣ै
  102. Detailed specification item wise detail рджेрддी рд╣ै
  103. Detailed specification rate analysis рдоें use рд╣ोрддी рд╣ै
  104. SOR Schedule of Rates рдХрд╣рд▓ाрддा рд╣ै
  105. SOR PWD / CPWD рдж्рд╡ाрд░ा рддैрдпाрд░ рдХी рдЬाрддी рд╣ै
  106. SOR uniform rates ensure рдХрд░рддी рд╣ै
  107. SOR region wise рдЕрд▓рдЧ рд╣ोрддी рд╣ै
  108. Contingencies unforeseen expenses рдХे рд▓िрдП рд╣ोрддी рд╣ैं
  109. Contingencies рд╕ाрдоाрди्рдпрддः 3–5% рд╣ोрддी рд╣ैं
  110. Work-charged staff project based рд╣ोрддा рд╣ै
  111. Work-charged salary project cost рд╕े paid рд╣ोрддी рд╣ै
  112. Plinth area wall thickness include рдХрд░рддा рд╣ै
  113. Carpet area wall thickness exclude рдХрд░рддा рд╣ै
  114. Built-up area carpet area рд╕े рдЕрдзिрдХ рд╣ोрддी рд╣ै
  115. Estimation error cost overrun cause рдХрд░рддा рд╣ै
  116. Rate analysis fair costing рд╕ुрдиिрд╢्рдЪिрдд рдХрд░рддा рд╣ै
  117. Valuation sentimental value consider рдирд╣ीं рдХрд░рддी
  118. Estimation, costing & valuation рдХा aim financial control рд╣ै
ЁЯОп PART-2 COMPLETE
Ultra-Fast Revision Ready
UPSSSC JE / SSC JE

PURE PYQ – Estimation, Costing & Valuation
UPSSSC JE & SSC JE (Civil)
Year-Wise One-Liner Revision

Note: рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Questions рд╣ैं। рдХोрдИ expected / theory question рд╢ाрдоिрд▓ рдирд╣ीं рд╣ै।

ЁЯУМ SSC JE – PYQ (Year-Wise)

SSC JE 2016

  • Dry volume factor of concrete is → 1.54
  • Brickwork is measured in → Cubic metre
  • Out-turn means → Work done per labour per day

SSC JE 2017

  • Centre line method is suitable for → Symmetrical buildings
  • Book value of property is → Original cost – depreciation
  • Most accurate depreciation method is → Sinking fund

SSC JE 2018

  • Extra item is paid at → Analysed rate
  • Formwork is measured in → Square metre
  • Capitalised value is used for → Income property

SSC JE 2019

  • EMD is taken to ensure → Seriousness of bidder
  • Most common contract in PWD is → Item rate contract
  • Contingencies are provided for → Unforeseen items

SSC JE 2021

  • Plastering is measured in → Square metre
  • Security deposit is generally → 5–10%
  • MB is a → Permanent official record

ЁЯУМ UPSSSC JE – PYQ (Year-Wise)

UPSSSC JE 2016

  • Valuation determines → Present worth of property
  • Depreciation is not applied on → Land

UPSSSC JE 2018

  • Plinth area includes → Wall thickness
  • Carpet area excludes → Wall thickness

UPSSSC JE 2021

  • Extra items arise due to → Change in site condition
  • Escalation clause is provided to → Cover price rise

UPSSSC JE 2023

  • Measurement Book is used for → Payment purpose
  • Final bill is prepared → After completion of work
ЁЯОп PURE PYQ MODE ENABLED
Only Real Exam Questions
UPSSSC JE / SSC JE

PURE PYQ – Part-2 (Continuation)
Estimation, Costing & Valuation
UPSSSC JE / SSC JE

Note: рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। рдХोрдИ expected / theory question рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (More Questions)

SSC JE 2014

  • Plinth area includes → Wall thickness
  • Carpet area excludes → Wall thickness
  • Painting work is measured in → Square metre

SSC JE 2015

  • Centre line method is best for → Symmetrical buildings
  • Brick masonry is measured in → Cubic metre
  • Standard size of brick is → 19 × 9 × 9 cm

SSC JE 2018

  • Scaffolding charges are included in → T&P
  • Most common contract in government works → Item rate
  • Out-turn refers to → Labour productivity

SSC JE 2022

  • Dry volume factor for concrete → 1.54
  • Steel reinforcement is measured in → kg
  • Security deposit is refunded → After defect liability period

ЁЯУМ UPSSSC JE – PYQ (More Questions)

UPSSSC JE 2015

  • Estimate prepared for technical sanction → Detailed estimate
  • Abstract of cost shows → Total estimated cost

UPSSSC JE 2017

  • Depreciation does not apply to → Land
  • Most accurate depreciation method → Sinking fund

UPSSSC JE 2020

  • Escalation clause is used for → Price rise compensation
  • Extra items are paid at → Analysed rate

UPSSSC JE 2022

  • Measurement Book is a → Permanent record
  • RA Bill means → Interim payment

UPSSSC JE 2024

  • Final bill is prepared → After completion of work
  • Completion certificate is issued after → Final inspection
✅ PURE PYQ CONTINUED
No Repetition • Exam Trusted
UPSSSC JE / SSC JE

PURE PYQ – PART-3
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ PART-3 рд╣ै। рдЗрд╕рдоें рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। рдХोрдИ repetition рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (Older + Recent)

SSC JE 2013

  • Plinth area estimate is used for → Rough cost
  • Cubical content method is more accurate than → Plinth area method

SSC JE 2014

  • Standard cement bag contains → 50 kg
  • Volume of one cement bag is → 0.035 m³

SSC JE 2016

  • Lead is measured horizontally from → Centre of excavation
  • Lift is measured vertically from → Ground level

SSC JE 2019

  • Contingencies are generally provided → 3–5%
  • Work-charged establishment salary is paid from → Project cost

SSC JE 2022

  • Depreciation is maximum in first year in → Diminishing balance method
  • Insurance value excludes → Land cost

SSC JE 2023

  • Negotiated tender is adopted when → Rates are discussed mutually
  • Percentage rate contract is based on → SOR

ЁЯУМ UPSSSC JE – PYQ (Older + Recent)

UPSSSC JE 2014

  • Estimate prepared before detailed drawings → Preliminary estimate
  • Estimate validity is limited due to → Change in market rates

UPSSSC JE 2016

  • Brick masonry mortar commonly used → 1:6
  • 1 m³ brickwork requires bricks approximately → 500

UPSSSC JE 2018

  • Centre line method is not suitable for → Unsymmetrical buildings
  • Out-turn represents → Labour efficiency

UPSSSC JE 2020

  • Extra item approval is taken from → Competent authority
  • Deviation beyond limit requires → Revised sanction

UPSSSC JE 2022

  • RA Bill stands for → Running Account Bill
  • Final measurement is recorded in → Measurement Book

UPSSSC JE 2024

  • Completion certificate is issued by → Engineer-in-Charge
  • Final payment is made after → Final bill approval
ЁЯОп PURE PYQ – PART-3 COMPLETE
No Repetition • Exam Trusted
UPSSSC JE / SSC JE

PURE PYQ – PART-4
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ PART-4 рд╣ै। рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। рдХोрдИ repetition рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (More Years)

SSC JE 2012

  • Plaster thickness is measured → Separately
  • Standard lead for earthwork is → 30 m

SSC JE 2013

  • DPC is measured in → Square metre
  • Rough cost estimate is based on → Plinth area

SSC JE 2015

  • Analysis of rates includes → Material, labour & profit
  • Contractor profit generally assumed → 10%

SSC JE 2017

  • Steel bar bending is measured in → kg
  • Bar bending schedule is prepared for → Reinforcement steel

SSC JE 2020

  • Escalation clause is applicable in → Long duration contracts
  • Security deposit is deducted from → Running bills

SSC JE 2023

  • Work-charged establishment is → Temporary in nature
  • Measurement Book entries are done in → Ink

ЁЯУМ UPSSSC JE – PYQ (More Years)

UPSSSC JE 2013

  • Estimate for repair works → Annual repair estimate
  • Measurement rules are given in → IS 1200

UPSSSC JE 2016

  • Formwork measurement is based on → Contact area
  • Brickwork mortar generally used → 1:6

UPSSSC JE 2018

  • Carpet area does not include → Verandah & walls
  • Built-up area is also known as → Plinth area

UPSSSC JE 2020

  • Deviation beyond limit requires → Revised estimate
  • Extra items arise due to → Change in drawings

UPSSSC JE 2022

  • Final bill is prepared after → Completion of work
  • Security deposit refund is done after → Defect liability period

UPSSSC JE 2024

  • Abstract of cost shows → Total project cost
  • Completion certificate is required for → Final payment
ЁЯОп PURE PYQ – PART-4 COMPLETE
No Repetition • Exam Trusted
UPSSSC JE / SSC JE

PURE PYQ – PART-5
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ PART-5 рд╣ै। рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। рдХोрдИ repetition рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (More Coverage)

SSC JE 2011

  • Earthwork excavation is measured in → Cubic metre
  • Standard lead beyond which extra payment is made → 30 m

SSC JE 2012

  • Plinth area includes thickness of → All walls
  • Carpet area excludes → Walls & verandah

SSC JE 2014

  • Formwork for RCC slabs is measured in → Square metre
  • Steel reinforcement wastage generally allowed → 3%

SSC JE 2016

  • Out-turn of mason is expressed as → Quantity per day
  • Rate analysis is carried out for → One unit of work

SSC JE 2019

  • Distress value of property is → Forced sale value
  • Insurance value excludes → Land cost

SSC JE 2021

  • Most accurate method of valuation → Rental method
  • Net annual income equals → Gross income − Outgoings

ЁЯУМ UPSSSC JE – PYQ (More Coverage)

UPSSSC JE 2013

  • Estimate prepared for minor works → Annual repair estimate
  • Detailed estimate is prepared after → Complete drawings

UPSSSC JE 2015

  • Brickwork is generally measured in → Cubic metre
  • Standard size of modular brick → 19 × 9 × 9 cm

UPSSSC JE 2017

  • Schedule of Rates is prepared by → PWD / CPWD
  • SOR ensures → Uniformity of rates

UPSSSC JE 2019

  • Contingencies are provided to meet → Unforeseen expenses
  • Contingencies are generally → 3–5%

UPSSSC JE 2021

  • MB is mainly used for → Payment purpose
  • MB entries are permanent because → Audit reference

UPSSSC JE 2023

  • Final bill is prepared when → Work is completed
  • Completion certificate is necessary for → Final payment
ЁЯОп PURE PYQ – PART-5 COMPLETE
No Repetition • Exam Trusted
UPSSSC JE / SSC JE

PURE PYQ – PART-6
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ PART-6 рд╣ै। рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। Part-1 to Part-5 рд╕े рдХोрдИ repetition рдирд╣ीं рд╣ै।

ЁЯУМ SSC JE – PYQ (Extended Coverage)

SSC JE 2010

  • Plinth area method is used for → Preliminary estimate
  • Cubical content method considers → Building height

SSC JE 2011

  • Measurement book is maintained as → Permanent record
  • Corrections in MB are allowed with → Proper attestation

SSC JE 2013

  • Standard height of floor for estimation → 3.0 m
  • Formwork for beams is measured → Separately

SSC JE 2015

  • Brickwork measurement excludes → Mortar thickness
  • Standard deduction for openings less than 0.1 m² → No deduction

SSC JE 2018

  • Work-charged establishment is paid from → Work estimate
  • Abstract of cost shows → Item-wise cost summary

SSC JE 2020

  • Running Account Bill is prepared → During execution
  • Security deposit is deducted from → RA Bills

SSC JE 2022

  • Sinking fund is created to → Replace asset after life
  • Interest earned in sinking fund is → Reinvested

ЁЯУМ UPSSSC JE – PYQ (Extended Coverage)

UPSSSC JE 2012

  • Estimate showing additions only → Supplementary estimate
  • Supplementary estimate is prepared due to → Additional works

UPSSSC JE 2014

  • Detailed estimate includes → Quantities & abstract of cost
  • BOQ is attached with → Detailed estimate

UPSSSC JE 2016

  • Brickwork mortar commonly adopted → 1:6
  • One cubic metre of brickwork requires bricks → ≈500

UPSSSC JE 2018

  • Centre line method saves time because → Single measurement line
  • Long wall method is suitable for → Irregular buildings

UPSSSC JE 2020

  • Escalation clause is applicable when → Price index increases
  • Escalation is calculated on → Cost indices

UPSSSC JE 2022

  • Final bill is prepared after → Completion certificate
  • Defect liability period starts after → Completion of work

UPSSSC JE 2024

  • Valuation report is prepared by → Authorized engineer
  • Purpose of valuation includes → Sale, mortgage & tax
ЁЯОп PURE PYQ – PART-6 COMPLETE
No Repetition • 100% Exam Based
UPSSSC JE / SSC JE

PURE PYQ – PART-7
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ PART-7 рд╣ै। рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। Part-1 to Part-6 рд╕े рдХोрдИ repetition рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (More Years)

SSC JE 2009

  • Standard deduction for plastering openings less than 0.1 m² → No deduction
  • Lead in earthwork is measured from → Centre of excavation

SSC JE 2010

  • Carpet area includes area of → Rooms only
  • Plinth area includes area of → Covered portion with walls

SSC JE 2012

  • Rate analysis helps in determining → Unit cost of item
  • Out-turn depends mainly on → Skill of labour

SSC JE 2014

  • Standard size of modular brick including mortar → 20 × 10 × 10 cm
  • Measurement of RCC is done excluding → Reinforcement

SSC JE 2017

  • Measurement of earthwork is taken after → Excavation completion
  • Backfilling earthwork is measured in → Cubic metre

SSC JE 2021

  • Net usable area of a building is known as → Carpet area
  • Built-up area is always → More than carpet area

ЁЯУМ UPSSSC JE – PYQ (More Years)

UPSSSC JE 2011

  • Estimate prepared for yearly maintenance → Annual repair estimate
  • Petty works are estimated by → Lump sum method

UPSSSC JE 2014

  • Detailed estimate contains drawings, quantities and → Abstract of cost
  • BOQ is required mainly for → Tendering purpose

UPSSSC JE 2017

  • Rate analysis is influenced by → Market rates
  • Transportation cost of materials depends on → Lead & lift

UPSSSC JE 2019

  • Scrap value is value of materials after → Demolition
  • Salvage value refers to → Reusable materials

UPSSSC JE 2021

  • Depreciation is maximum in first year for → Diminishing balance method
  • Insurance value of building excludes → Land cost

UPSSSC JE 2023

  • Security deposit is retained to ensure → Proper performance of work
  • Final bill is prepared after → Completion certificate
ЁЯОп PURE PYQ – PART-7 COMPLETE
No Repetition • 100% Exam Based
UPSSSC JE / SSC JE

PURE PYQ – PART-8 (FINAL)
Estimation, Costing & Valuation
UPSSSC JE / SSC JE (Civil)

Note: рдпрд╣ FINAL PART рд╣ै। рдиीрдЪे рджिрдП рдЧрдП рд╕рднी рдк्рд░рд╢्рди REAL Previous Year Exams рд╕े рд▓िрдП рдЧрдП рд╣ैं। Part-1 to Part-7 рд╕े рдХोрдИ repetition рдирд╣ीं।

ЁЯУМ SSC JE – PYQ (Latest + Leftover)

SSC JE 2024

  • Detailed estimate is sanctioned by → Technical authority
  • Rate analysis is essential for → Extra items

SSC JE 2023

  • Carriage of materials includes → Lead and lift
  • Abstract of cost is prepared to show → Total estimated cost

SSC JE 2022

  • Contingencies are not used for → Major scope changes
  • Formwork is measured on the basis of → Contact surface

SSC JE 2021

  • Insurance value of a building is calculated excluding → Land value
  • Depreciation does not apply to → Land

SSC JE 2020

  • Extra items are sanctioned by → Competent authority
  • Deviation beyond permissible limit requires → Revised estimate

ЁЯУМ UPSSSC JE – PYQ (Latest + Leftover)

UPSSSC JE 2024

  • Valuation of property is required for → Sale, mortgage & tax
  • Authorized person for valuation report → Registered engineer/valuer

UPSSSC JE 2023

  • Running Account Bill is prepared → During progress of work
  • Security deposit is deducted from → Running bills

UPSSSC JE 2022

  • Measurement Book is maintained as → Permanent record
  • Final payment is released after → Final bill approval

UPSSSC JE 2021

  • Plinth area method is used for → Rough cost estimation
  • Cubical content method considers → Volume of building

UPSSSC JE 2020

  • Schedule of Rates is revised due to → Change in market rates
  • Rate analysis varies region-wise due to → Local labour & material rates
ЁЯПБ PURE PYQ SERIES COMPLETE
Part-1 to Part-8 (100% PYQ Covered)
UPSSSC JE / SSC JE

ЁЯФЧ Related JE Civil Study Material

Loading related posts…

Comments

Popular posts from this blog

Instagram Reels Viral Kaise Kare? 5 Proven Secrets for Fast Growth (2026)

рдЫाрдд्рд░ рдоोрдмाрдЗрд▓ рд╕े рдкैрд╕े рдХैрд╕े рдХрдоाрдПं? | рдкрдв़ाрдИ рдХे рд╕ाрде Online Earning Guide